DBFO (Design, Build, Finance and Operation) of new co-generation facility, ready to serve Florence 1650-bed Careggi General Hospital and its vicinity with 125.000 Mwh/year combined energy supply (power, heat and cooling).
New co-generation plant PPP contract entails installation of gas turbines, accessories, transformers, IT controls, 2,5 km of pipeline for energy and steam distribution to endpoints, plus 15-year operation and maintenance.
Besides availability of a brand-new energy plant and supply network, a clear benefit for Awarding Authority results in a 15% estimated average annual savings made from the total actual energy bill paid by Hospital, equivalent to approximately 1 million euro/year.
Concession was awarded on December 2005, plant commissioned in 2012 and operational since then.
Project carried out by Alberto Germani as PPP Task Force member of the Italian Ministry of the Treasury.
Committente: Azienda Ospedaliera Careggi, Florence (Hospital Authority)
Anno: 2004 - 2005
Valore (in USD): EUR 25.000.000 (CAPEX)
Florence Hospital Co-Generation Power Facility (Italy)
DBFO (Design, Build, Finance and Operation) of new co-generation facility, ready to serve Florence 1650-bed Careggi General Hospital and its vicinity with 125.000 Mwh/year combined energy supply (power, heat and cooling).
New co-generation plant PPP contract entails installation of gas turbines, accessories, transformers, IT controls, 2,5 km of pipeline for energy and steam distribution to endpoints, plus 15-year operation and maintenance.
Besides availability of a brand-new energy plant and supply network, a clear benefit for Awarding Authority results in a 15% estimated average annual savings made from the total actual energy bill paid by Hospital, equivalent to approximately 1 million euro/year.
Concession was awarded on December 2005, plant commissioned in 2012 and operational since then.
Project carried out by Alberto Germani as PPP Task Force member of the Italian Ministry of the Treasury.